Jindabyne

Locality
Jindabyne, NSW
Year
2009 / 2010
Voltage / Function
Jindabyne East 66/11kV Zone Substation (20 MVA)
Asset Owner
Essential Energy
Scope

Civil and Electrical Construction
CPP was contracted to perform all Civil and Electrical works for the following :
 - 2 x 66kV Incomer Line Bays including all primary and secondary works
 - 2 x 66/11kV Transformer Bays including all primary and secondary works

CPP PM -  Davin Berelowitz