Sleaford

Locality
Port Lincoln, 300km West of Adelaide, South Australia
Year
2005
Voltage / Function
132/33kV Substation
Asset Owner
ElectraNet
Scope

Design & Construction of grid connection for Cathedral Rocks Wind Farm comprising :

  •   1 x 132kV circuit breaker bay,
  •   1 x 75MVA power transformer;
  •   1 x 33kV exit to connect the wind farm;
  •   Control building;
  •   Remote protection upgrade;
  •   Substation civil works.