East Rowville Terminal Station


2x 150MVA 220/66/11kV

POWER TRANSORMERS


352 DAYS

WORKED ON THE PROJECT



385x

NETWORK AUTHORITY PERMITS


220kV and 66 kV

SWITCHGEAR INSITU



17 of 25

COMMISSIONING STAGES COMPLETE


PROJECT HEADED BY AUSNET SERVICES


Overview
CPP Scope of Works

Deliverables

  • Commissioning
  • Construction
  • Scheduling
  • Project Management

  • 352 of 460 days, worked on the project to date
  • 17 of 25 commissioning stages complete
  • 385 network authority permits including 102 network outages to date
  • An average of 1 outage every 3.5 workdays (network restoration time pressures and outage frequency challenges managed well by the team without affecting quality, safety, or wellbeing)

2023 – 2025
Design and construction of 330kV Substation, OHL 330kV Connection to Munmorah Substation and 850MW BESS.
Colongra, NSW
2020 – 2021
Large solar PV system with single-axis tracking and ground-mounted panels, generating 395 GWh annually.
Suntop, NSW
2020 – 2023
Australia’s largest solar farm, with a 460 MWp capacity and a 270 MW / 540 MWh battery.
Hopeland, Queensland