Conpower

Ross Primary Plant Replacement


275kV/132kV 66/33kV

PRIMARY PLANT REPLACEMENTS


31

STAGES V’S 15 COMPLETED TO DATE



13,500

TERMINATION COMPLETED


POWERLINK

LEADING PROJECT



222

FOUNDATION TOTAL V’S 165 COMPLETED TO DATE


40,000M

CABLES PULLED TO DATE


Overview
CPP Scope of Works

Deliverables

  • Construction

  • 31x stages in total, 15x completed to date
  • 222x foundations in total,164x completed to date
  • 40,000m of cables pulled
  • 13,500 terminations completed
  • 45,000 hours worked to date with no LTI or MTI’s (safety concerns)
  • 4,000 hrs in training

2023 – 2025
Design and construction of 330kV Substation, OHL 330kV Connection to Munmorah Substation and 850MW BESS.
Colongra, NSW
2020 – 2021
Large solar PV system with single-axis tracking and ground-mounted panels, generating 395 GWh annually.
Suntop, NSW
2020 – 2023
Australia’s largest solar farm, with a 460 MWp capacity and a 270 MW / 540 MWh battery.
Hopeland, Queensland